Current location - Trademark Inquiry Complete Network - Futures platform - The scale of Hong Sheng refining and chemical integration project has suddenly shrunk? How are the projects such as Hengli and Wanhua progressing?
The scale of Hong Sheng refining and chemical integration project has suddenly shrunk? How are the projects such as Hengli and Wanhua progressing?
On August 8, 20 19, Oriental Hong Sheng announced that the board meeting of the company deliberated and passed the Proposal on Optimizing and Adjusting Part of the Construction Content of Hong Sheng Refining and Chemical Integration Project, and partially adjusted some of the facilities of the project.

After optimization and adjustment,

The main industrial scales of the project are160,000 tons/year crude oil processing, 2.8 million tons/year PX and110,000 tons/year ethylene.

Scale adjustment of diesel wax oil hydrocracking and other 10 sets of process units;

Cancel 8 units such as lube oil hydroisomerization dewaxing and ethylene vinyl acetate copolymer (EVA)/ polyethylene (PE);

Scheme change of power generation and hydrogen production system;

The total refining process is moderately optimized, and the proportion of refined oil in crude oil processing is reduced from 37% before adjustment to 3 1% after adjustment, which can provide more basic chemical raw materials;

The total investment of the project decreased from 77.47536 billion yuan before adjustment to 67.66396 billion yuan after adjustment;

It is estimated that after the project is put into production, the average annual profit will increase from about1010.30 billion before adjustment to about125.6 billion after adjustment, and the average annual net profit will increase from about 7.59 billion before adjustment to about 9.42 billion after adjustment.

In addition, on the same day, the Plan for Non-public Offering of A Shares by Jiangsu Oriental Hong Sheng Co., Ltd. in 20 19 (Revised Draft) was also published. The number of shares to be issued non-publicly does not exceed 20% of the total share capital, that is, it does not exceed 805,865,438+00,644 shares (inclusive), and the total amount of funds raised (inclusive) does not exceed. Among them, Hong Sheng Zhou Su intends to participate in the subscription in cash, and the subscription amount does not exceed 654.38+0.5 billion yuan.

It is reported that Hong Sheng Refining & Chemical160,000 tons/year refining & chemical integration project is located in Petrochemical Industrial Park, Xu Wei New District, Lianyungang City, with a total investment of about 67.7 billion. Hong Sheng Refinery (Lianyungang) Co., Ltd. invested in the construction, and the planned construction period is 36 months. It is estimated that 202 1 will be completed and put into production.

The project plans to adopt international advanced process package technologies such as Axens, Chevron, LUMMUS, DuPont, ExxonMobil, Shell and Lyondellbasell. The factory technology has reached the international leading level; The gasoline and diesel products of the project will all meet the national VI standard; The PX and MEG raw materials of the project will be used as the upstream raw materials of the company's core business, which will promote the company to build a new high-end textile industry chain of "crude oil refining -PX/ ethylene glycol -PTA- polyester-chemical fiber".

Reasons for scheme adjustment

The Board of Directors of Oriental Hong Sheng said that the optimization and adjustment plan of this project embodies the idea of "refining and chemical integration, focusing on chemical industry" and conforms to the national industrial policy and industry development trend. After the adjustment of the project, the total investment estimate is reduced and the economic benefit is improved, which can give full play to the advantages of refining and chemical integration and is in line with the interests of listed companies and all shareholders.

According to the Oriental Hong Sheng, the single-line scale of Hong Sheng refining and chemical integration project is160,000 tons, which is the largest single-line capacity in China at present. The project is an important part of the company's industrial chain integration development strategy, which will open up industrial chains such as crude oil refining, high-end chemicals, polyester and chemical fiber, realize the qualitative change from straight chain of gasoline and diesel to network industrial chain, and drive the development of downstream high-end chemical materials.

The total amount of funds raised from the above non-public offering will be used for Hong Sheng Refining & Chemical (Lianyungang) Co., Ltd.160,000-ton refining & chemical integration project. For the purpose of this fundraising, Oriental Hong Sheng said that on the one hand, it is to respond to the national policy of developing high-end petrochemical products and promoting the transformation and upgrading of the petrochemical industry, and on the other hand, it is to implement the vertical integration strategy of the company's industrial chain to realize the coordinated development of industry consolidation.

Important Time Nodes of Hong Sheng Refining and Chemical Integration Project

2018 September 17, the project was approved by the Development and Reform Commission of Jiangsu Province;

2018165438+17 October, the research meeting and the signing ceremony of Hong Sheng refining and chemical integration project were held;

20181211,the project EIA report was approved by the Ministry of Ecology and Environment;

20 19 12 14, the project officially started construction, and it is planned to be put into production at the end of 20021;

2019 65438+1October 15, the kick-off meeting of the overall design of the project was held, and the overall design work officially started;

2065438+On March 8, 2009, Petrochemical Industry, a wholly-owned subsidiary of Oriental Hong Sheng, signed an equity purchase agreement with Zhou Su and Hong Sheng Petrochemical of Hong Sheng, and acquired 0/00% equity of Hong Sheng Refinery10813200 yuan.

2065438+March 1 1 In 2009, the lead bank of Hong Sheng Group's refining and chemical integration project signed a contract for cooperation and comprehensive strategic cooperation, and the project won a syndicated loan of 55 billion yuan;

On April 3, 20 19, Oriental Hong Sheng announced that it plans to issue green corporate bonds in a non-public way, with a total par value of no more than 3 billion yuan (including 3 billion yuan), which will be used for the construction of refining and chemical integration projects in Hong Sheng;

On April 2, 20 19, Oriental Hong Sheng announced that it planned to increase the capital of Hong Sheng Refining & Chemical (Lianyungang) Co., Ltd. by 7 billion yuan, increasing the registered capital of Hong Sheng Refining & Chemical from 6,543,800 yuan to 8 billion yuan;

June 1, 2065438,160,000 tons/year atmospheric and vacuum distillation unit, 3 10/00,000 tons/year 1# continuous reforming unit, and coal coke gasification combined unit started;

On June 4th, 20 19, Lianyungang Hong Sheng Refining and Chemical Fund signed a contract of 2.5 billion yuan;

20 19,17,2065438 The wharf project of Hong Sheng refining and chemical integrated port storage project with a total investment of 2.68 billion yuan was officially started.

Hengli petrifaction

On August 7th, the 6,543,8+0.5 million tons/year ethylene plant substation of Dalian Hengli Petrochemical Project, which was built by Sijian Electric Instrument Company, realized the installation of the first batch of key equipment-electrical panels and cabinets at one time, and won unanimous praise from the owners.

The 654.38+500,000 tons/year ethylene project of Hengli Petrochemical successfully completed the hoisting of cracking furnace module.

On July 27th, the 6.5438+0.5 million tons/year ethylene project of Dalian Hengli Petrochemical Company in Liaoning Province, which was undertaken by Sijian Company, was safely and smoothly hoisted in place through the efforts of all the employees involved in the war.

According to reports, the ethylene project department of Dalian Hengli Petrochemical Co., Ltd. of Sijian, according to the delivery time provided by the owner, the construction department and the technical department arranged the construction plan in advance, compiled the hoisting scheme of large equipment, and reported it to the supervision department for review. 1350 ton crawler crane with counterweight and 750 ton overloaded crawler crane are selected for hoisting. There are 9 liquid furnaces, and each pyrolysis furnace has 7 convection chamber modules, totaling 63 groups. According to the foundation engineering test report, the foundation bearing capacity of the site is 26 tons/m2, which meets the requirements of all convection modules and smoke hoods.

The convection chamber of the cracking furnace is located above the radiation section of the furnace body. Each convection chamber of the cracking furnace consists of 7 groups of convection modules and 1 group of smoke hoods. It is characterized by high height, heavy weight and large volume, and must be hoisted in an orderly manner by parts and sections from bottom to top.

In order to ensure the safety of aerial work, the Fourth Construction Project Department arranged to weld cantilever beam support scaffolding on the ground module. The erection team completed the scaffold construction on the ground and delivered it to the supervision company for inspection before hoisting, which provided a guarantee for the subsequent construction safety.

The core stirred reactor of high-density polyethylene plant of 65438+500,000 tons/year ethylene project of Hengli Petrochemical Company started smoothly.

2065438+On the morning of August 4, 2009, Sichuan Kexin Electromechanical Co., Ltd. successfully loaded the 400,000-ton/year high-density polyethylene core stirring reactor customized for Dalian Hengli Petrochemical (Dalian) Chemical Co., Ltd. in Shifang Economic Development Zone.

There are 7 sets of "big" equipment shipped this time, which are the core stirring reactors of the 400,000-ton/year high-density polyethylene plant of the 654.38+500,000-ton/year ethylene project of Hengli Petrochemical (Dalian) Chemical Co., Ltd., including the first reactor, the second reactor, the third reactor, the powder treatment tank and other large pressure vessel equipment, with a total weight of 700 tons. Among them, four sets of equipment each weigh more than 170 tons, and the maximum overall size is 32.55m *7.5m *7.6m.

It is understood that the 654.38+0.5 million tons/year ethylene project of Hengli Petrochemical (Dalian) Chemical Co., Ltd. is the second phase project newly built by Hengli Petrochemical in Changxing Island, Dalian. The first phase of the project is a 20-million-ton refining and chemical integration project, which is a national key project to revitalize the old industrial base in Northeast China.

Zhongke refining

Zhongke refining and chemical integration project will be fully completed by the end of the year.

On August 7th, China Petrochemical Zhongke Project held a mobilization meeting of "150 days" labor competition to fully implement the spirit of Chairman Dai's series of speeches on the construction of Zhongke Project, mobilize all participating units and personnel, and launch a sprint to the goal of "building China traffic in an all-round way by the end of the year", and resolutely ensure the implementation of the decision-making and deployment of the party group of the group company.

In August, the overall image progress requirements of the project are: 80% steel structure installation, 60% equipment installation and 40% prefabricated process pipeline installation.

On the morning of August 5th 10:30, the upper head of the 4,200,000-ton/a catalytic cracking unit reaction settler of Zhongke Project, which was contracted by Luo Yang Engineering Company, installed by Shi Jian Company and hoisted by the shipping company, was hoisted in place, marking the basic completion of the installation of the "two-reactor" reaction settler equipment of the catalytic cracking unit.

On August 7th, it was learned from Sijian Company that V-4221flash tank, the last large-scale equipment of 35HDPE plant in Zhongke Refining & Chemical Company, which was undertaken by Zhongke Project Department of Sijian Third Engineering Company, was installed safely and smoothly through the joint efforts of all employees involved in the construction, and the installation of large-scale equipment of 35HDPE plant in Zhongke Refining & Chemical Company was successfully completed.

The total weight of the reaction settler is 994 tons, the overall height is 66.32 meters, and the diameter of the reaction settler changes from 1.9 meters to the maximum of 9 meters from bottom to top four times, showing a cone shape with big top and small bottom. The reaction settler is installed in a 50.5-meter-high "well" shaped reinforced concrete frame foundation, and the top standard after installation is as high as 68.2 meters. The shell of the reaction settler is prefabricated in five sections on the ground, the internal components are assembled, and the steel structure of the external platform is modularized. After prefabrication is completed, it will be hoisted in place in sections.

The upper head of the reaction settler hoisted by sections is 9 meters in diameter, 4.75 meters in height and weighs 1.38 tons. Hoisting with 65,438+0,250 tons crawler crane. Because the hoisting position is extremely narrow, a 260-ton truck crane is used in the hoisting process to facilitate the completion of the hoisting task.

From the first stage hoisting of the reaction settler on May 27th to the smooth installation of the upper head on August 5th, all the contractors of the catalytic cracking unit overcame the difficulties of severe conditions such as extremely hot weather in Zhanjiang, narrow working site, difficult hoisting technology, high requirements for quality and safety, high operating temperature in the reactor, sultry and so on, and constantly accelerated the prefabrication and installation progress. All the staff cooperated closely, rain or shine, and successfully completed the site of the reaction settler, the core equipment of the catalytic cracking unit, day and night.

Project review

The Zhongke Refining and Chemical Project with a total investment of tens of billions of RMB was once called the largest petrochemical project under construction in China. The project passed the EIA in March of 20 1 1 and was approved by the National Development and Reform Commission of China. Zhanjiang East Island started construction in June, 20 1 1. However, due to factors such as falling international oil prices and serious excess refining capacity, the project construction almost stopped.

From July 2065438 to July 2006, China Petrochemical Group set up a leading group for refining and chemical integration in Maoming to make overall consideration of the resource allocation and refining and chemical development in Maoming, Zhanjiang and other regions, which enabled the construction of Zhongke refining and chemical projects to enter the fast lane.

At the end of 20 16, the preparatory group of zhongke refining and chemical project in Zhanjiang, Guangdong province disclosed to the media that the overall design of zhongke refining and chemical project had been approved. According to the overall design, the total construction scale of Zhongke Refining and Chemical Project is oil refining100000 tons/year and ethylene 800000 tons/year. The core process of "atmospheric and vacuum distillation+hydrocracking+total residue hydrogenation+catalytic cracking" is adopted in oil refining, and the product scheme of "ethylene derivative HDPE+EO/EG+ ethanolamine and all propylene derivative PP" is adopted in chemical industry.

2065438+March 2008, China Petrochemical Refining and Chemical Engineering announced that the Group had recently signed a number of EPC general contracts with Zhongke (Guangdong) Refining and Chemical Company for the chemical industry and power station of Zhongke Guangdong Refining and Chemical Integration Project.

The project is located in Zhanjiang City, Guangdong Province, China. The main work scope of this contract includes: 800,000 tons/year steam cracking ethylene plant, 400,000 tons/year cracking gasoline hydrogenation plant, 550,000 tons/year polypropylene plant, 350,000 tons/year high-density polyethylene plant, 250,000 tons/year EO and 400,000 tons/year EG plant, 654.38 million tons/year EVA plant and 654.38 million standard units.

Liaoning baolai

Daming Heavy Industry successfully delivered the stirred reactor of Liaoning Bora 654.38+00,000 tons/year ethylene project.

2065438+On August 2, 2009, three stirred reactors of Liaoning Baolai/KLOC-0 1000000000 tons/year ethylene project undertaken by Daming Heavy Industry were successfully shipped.

The three reactors are all stirred reactors, and the medium in the reaction is mainly HDPE+ ethane. The diameter of the equipment is 4700mm, the length is 17250mm, and the weight of a single reactor is 1 10 ton. The equipment has a special structure and very high technical requirements: the equipment body is covered with a half tube, which requires high assembly requirements; The welding workload between the semi-pipe and the equipment body is large; There are more than 60 turns and a half tubes in a single device, and the total length of welding seam reaches1950m. The assembly accuracy of the agitator mounting port is also very high. The verticality tolerance between the agitator mounting flange and the cylinder axis is less than 0.0 1, and the coaxiality error between the agitator mounting flange and the cylinder axis is less than 2mm. Coaxiality error of upper and lower mounting flanges of agitator < <1mm.

The successful manufacture of such high-tech and super-large equipment depends on the strong technical force, high-quality and high-skilled production team and strict quality team of Daming Heavy Industry. The customer management team guided the whole process and made outstanding contributions to quality and schedule control.

The PE equipment hoisting of Liaoning Baolai light hydrocarbon comprehensive utilization project was successfully completed.

On August 1 day, 18, the last module (the fourth module) of the 107-meter-high degasser frame steel structure in the 450,000-ton/year LLDPE plant area of the light hydrocarbon comprehensive utilization project of Liaoning Baolai Chemical Co., Ltd. was successfully assembled, and the completion of the installation of the fourth module also marked the successful completion of the hoisting work of the whole PE plant area. From planning and deployment to assembly, hoisting and installation, the whole construction process witnessed the hard work of all managers and operators of Bora project department and construction team, and witnessed the tireless work spirit of thirteen builders in hot summer.

The overall weight of the steel structure of the degassing bin is 1 170 tons, the equipment of the degassing bin is 320 tons, the installation height of the steel structure is 32.6 meters-107 meters, the overall frame is designed as an ultra-high steel structure, and the steel columns are all welded cross steel, and the weight of a single main column reaches 27 tons. Therefore, the project department decided to prefabricate the steel structure in the factory and transport it to the construction site for assembly.

In the whole construction process, risk factors and operational risks are under control, and many difficulties and problems are encountered in the construction process, such as the installation of weighing modules, the ultra-high lifting height of equipment passing through steel frame, and the ultra-large frame size. Continuous rainy weather, material supply can not be timely and other constraints. In order to ensure the quality and progress, the project department makes timely deployment and coordination. In terms of operation, the whole team implements two shifts and 24-hour uninterrupted welding. In terms of technology, the project department organized many discussions and demonstrations in the form of special meetings to ensure the feasibility and safety of hoisting and installation. This series of efforts embodies the collective cohesion of the six companies and the spirit of Qi Xin's concerted efforts and common progress, ensuring the successful completion of the hoisting work of large PE devices.

Xinpu olefin

Xinpu olefin light hydrocarbon comprehensive utilization project will soon be put into trial operation.

According to the latest news, Taixing Xinpu olefin comprehensive utilization project with an annual output of165438+100000 tons of light hydrocarbons has entered a tense stage of unit commissioning and will be put into production in August, which indicates that Taixing Economic Development Zone will become the seventh "big ethylene" chemical park in China.

The project started construction in June, 2065438+2006 and took three years to complete. With a total investment of 5.5 billion yuan, it can produce 650,000 tons of ethylene, 6.5438+200,000 tons of propylene, 6.5438+450,000 tons of hydrogen, 45,000 tons of C4, 30,000 tons of methane and 45,000 tons of cracked gasoline. It is estimated that the annual sales revenue will increase by 654.38 billion yuan.

This is the first plant in China to produce ethylene by cracking ethane and propane. The ethylene yield is as high as 80.5%, far exceeding the 35% obtained from naphtha in the traditional process. In addition, the capacity of a single gas cracking furnace in this project is the largest in the world at present.

It is expected that enterprises in Taixing Economic Development Zone will realize self-sufficiency and get rid of dependence on imported ethylene raw materials, and extend downstream to PVC, polystyrene and other products. At the same time, it will promote the layout and level of the chemical industry in the park and even Taizhou, and help the rapid development of the regional economy.

Because the olefin project is known as "the largest olefin" and plays an important role in the industry, not only because ethylene is a resource product with strong industrial chain correlation in the chemical industry, but also because it has the characteristics of complex project equipment, high technology content and high investment intensity, the 165438+ 1 100 million tons light hydrocarbon comprehensive utilization project completed this time is rated as "extremely symbolic".

Wanhua chemistry

The particle mixing bin of 6353 device of Wanhua Chemical HDPE Project was successfully hoisted.

On July 23rd, the hoisting of the particle mixing bin of HDPE plant of Wanhua Chemical with an annual output of 350/300,000 tons of high-density polyethylene/polypropylene project, which was built by Sinochem Liu Jian Ningbo Branch, was successfully completed.

The lifting weight of the granular material mixing bin is 33 tons, the height is 3 1 m and the diameter is 8 meters. Because July is the key moment for all construction units to catch up with the construction period, and the site situation is complicated, it is necessary not only to overcome the problem of the transportation route of equipment entering the site, but also to choose the appropriate crane occupation point. Therefore, before the silo hoisting, the technicians, after accurate calculation and repeated argumentation, decided to adopt the hoisting scheme of 350-ton overhead truck crane and 80-ton crawler crane. At the same time, they communicate and coordinate with all units, plan transportation routes, arrange hoisting schemes, and strive to ensure smooth roads without affecting the normal construction of all construction units.

The aggregate homogenization frame has 14 silos, and the first batch is hoisted by two silos. The success of this hoisting marks the official start of the silo installation project of HDPE project.

With the timely completion of underground pipelines and steel structures, the installation of process pipelines of yantai wanhua Chemical Polyurethane Industrial Chain Integrated Ethylene Plant, which was built by the Tenth Construction Company, has started one after another.

The diameter of the process pipeline in this project is 6,543,800+0000 inches, of which the welding of special materials for ultra-high pressure steam pipeline is expected to reach 30,000 inches.