Current location - Trademark Inquiry Complete Network - Futures platform - What are the procedures for fire acceptance? What tests is the quality inspection station responsible for?
What are the procedures for fire acceptance? What tests is the quality inspection station responsible for?
I. Information preparation

1, fire protection design audit opinion;

2, fire inspection opinions;

3, fire safety management system;

4. Fire evacuation plan;

5. Other drawings that need to be explained.

Two. Acceptance organization

Design, supervision and construction units

Three. Accept cooperation

1. Division of labor among professionals (water, electricity, ventilation, main control room, water pump room)

2. All staff are ready (walkie-talkie, electrician, searchlight, ladder, hand-reported key, shutter key, fire elevator key, smoke exhaust valve reset tool, water gun, pressure gauge, etc.). )

3. Record the emergency broadcast notice.

4. Diesel generator debugging preparation

Four. Acceptance summary

5. Site cleaning and fire control system reset.

The testing station is responsible for testing the materials and equipment used by the fire installation and construction company. If it is qualified, it can also be tested for fire protection installation.