The second phase of the construction of Hefei Airport is in progress and open to traffic. According to relevant public information inquiries, in mid-May 2022, the terminal pile foundation and ancillary projects had completed an output value of approximately 65.04 million yuan (accounting for 21.19% of the contract value). An online car-hailing parking lot of 40,000 square meters and a car storage yard of 7,095 square meters have been built. The reconstruction of the approach road (Baotong Road) has been completed and opened to traffic on May 8.