Current location - Trademark Inquiry Complete Network - Tian Tian Fund - How to handle the preliminary procedures of the new school project?
How to handle the preliminary procedures of the new school project?
We need to go through the following preliminary procedures to do the new school project, that is, the housing construction project. The land used by schools has taken the place of birth as an example.

First, we need to measure the location of the school. We must measure the red line and the terrain.

After the survey, we will apply to the Ministry of Natural Resources for land pre-examination and site selection advice.

At the same time, we must prepare the project proposal and apply to the development and reform department for approval. Only when the project is approved can you have an ID card.

After the establishment of the project, in the process of applying to the natural resources department for land pre-examination and site selection, we also compiled the feasibility study report of the project. We should make a plan for the feasibility study report of this project, that is, a master plan. What is our building area? What is our floor area ratio? What are our architectural factors? We should have a standard general plan, and then our feasibility study will be perfect.

In the process of compiling the feasibility study, we can also carry out disaster assessment and mine suppression.

We need to process a preliminary investigation report.

After preliminary investigation, we can design the scheme. In the preliminary work of building a house (school), we should have a global view and grasp the whole project.

For housing projects, we need to make green building plans and renewable energy plans.

We should make a soil and water conservation plan and report it for approval.

Involving land acquisition and demolition, it is necessary to prepare a social stability risk assessment report and review the risk analysis report, which is an assessment report.

If it involves forest land, it is necessary to apply for a feasibility study report on requisition and occupation of forest land, and it must be approved by the forestry department. If it is a permanent occupation of forest land, it should be reported to the forestry department for approval.

We need to do the design, which is divided into three stages: scheme design, preliminary design and construction drawing design. After the preliminary design is made, experts should be organized to review the preliminary design, which is the preliminary plan. We will submit the preliminary design evaluation report and preliminary design results to the development and reform department, and then give us a reply to the preliminary design.

In this process, we must apply for approval of land use after completing these preliminary work.

After the land is submitted for approval, the construction land planning permit, construction project planning permit and construction permit can be handled. With these permits, the start of our project will be legal. If we haven't gone through these procedures, we have already started, so we must go through these procedures.

The perfection of these procedures is of great significance to the promotion of our project, the acceptance of our project and the implementation of our funds! You can consult us if you have any questions.

The respondent of this paper is Zhong Gong, an expert in engineering communication network, who has rich experience in handling the pre-project work procedures. In recent years, he has presided over or participated in the summary report of soil and water conservation monitoring/soil and water conservation facilities acceptance report of a primary school campus relocation project in Nandan County, and the evaluation report of energy saving report of a school project in Wuming District, Nanning, an education investment company in Guangxi.