Current location - Trademark Inquiry Complete Network - Tian Tian Fund - Regulations of Kunming Municipality on Urban Water Supply Management (202 1)
Regulations of Kunming Municipality on Urban Water Supply Management (202 1)
Chapter I General Provisions Article 1 In order to strengthen the management of urban water supply and water use, ensure the safety of urban water supply and water use, and safeguard the legitimate rights and interests of both water supply and water use, these Regulations are formulated in accordance with the Water Law of People's Republic of China (PRC), the Regulations on Urban Water Supply and other laws and regulations, and combined with the actual situation of this Municipality. Article 2 These Regulations shall apply to urban water supply and related management activities within the administrative area of this Municipality. Article 3 The management of urban water supply in this Municipality follows the principles of rational development and scientific protection of water sources, planning and water conservation, giving priority to ensuring residents' domestic water use, coordinating industrial and other water use, and encouraging the adoption of advanced water supply and water-saving facilities and equipment. Article 4 The people's governments of cities and counties (cities, districts) shall incorporate urban water supply into the national economic and social development plan, increase financial input, strengthen the development and construction of public water supply sources and emergency standby water sources, and gradually promote the interconnection of water sources and the integration of urban and rural water supply. Encourage multiple channels to raise funds for the construction and renovation of water supply facilities and equipment. Article 5 The municipal water administrative department is the municipal administrative department of urban water supply and water use, responsible for the overall management of urban water supply and water use in this city, and supervising and guiding urban water supply and water use in counties (cities, districts).

The supervision and management of urban public water supply and water use in the area covered by urban public water supply pipe network shall be the responsibility of the municipal administrative department of water supply and water use; The supervision and management of urban public water supply and water use in other areas shall be the responsibility of the administrative department of urban water supply and water use in counties (cities, districts).

The supervision and management of self-built water supply and secondary water supply is the responsibility of the county (city, district) urban water supply and water administration department.

Development and reform, public security, finance, natural resources planning, ecological environment, health, housing and urban and rural construction, emergency, market supervision and other administrative departments shall, according to their respective responsibilities, do a good job in urban water supply management. Chapter II Water Supply Planning and Construction Article 6 The administrative department of urban water supply and water use of a city or county (city, district) shall, within the scope of management responsibilities, work out a special plan for urban water supply in conjunction with the relevant administrative departments of development and reform, natural resources planning, urban and rural housing construction, ecological environment, etc., and organize its implementation after being submitted to the people's government at the same level for approval. Seventh urban public water supply projects are an important part of urban infrastructure, and should be implemented simultaneously with the overall planning and construction of land and space. Eighth city water supply project is completed, it shall be organized in accordance with the relevant provisions of the acceptance; Without acceptance or unqualified acceptance, it shall not be put into use. Ninth city and county (city, district) administrative departments of urban water supply and water use shall establish and improve the archives of urban water supply pipe network facilities and equipment management; Belonging to underground pipelines, the natural resources planning and management department shall incorporate them into the management of urban underground pipeline information base.

The construction unit of urban water supply project shall, within three months after the completion and acceptance of urban water supply project, hand over the project completion files to the urban construction archives management department. Tenth new residential buildings should be designed and built in accordance with the requirements of "one meter for one household, one meter outside the house". If the "one meter for one household, one meter for one household" is not implemented in the built houses, the urban public water supply units shall be reformed in a planned way, and the specific scheme shall be formulated by the people's governments of cities and counties (cities, districts). Chapter III Management of Water Supply Article 11 Units engaged in urban water supply business activities may engage in business activities only after being registered by the market supervision and management authorities. Article 12 urban water supply units shall regularly submit the production and operation, the operation of facilities and equipment and relevant statistical data to the local urban water supply and water use administrative department, provide qualified production and domestic water to water users and individuals in accordance with the relevant national technical standards and norms, and accept the supervision of the urban water supply and water use administrative department, health, market supervision and the public. Thirteenth urban water supply units shall set up water supply network pressure measuring points in accordance with the provisions of the state, and do a good job in water pressure monitoring to ensure that the water supply network pressure meets the standards prescribed by the state.

City water supply units shall maintain safe, continuous and stable water supply, and shall not stop water supply without authorization.

When it is really necessary to stop water supply due to engineering construction and equipment maintenance, the urban water supply unit shall report to the competent administrative department of urban water supply and water use for approval, and notify the water users and individuals 24 hours in advance.

When the water supply facilities and equipment fail, the urban water supply unit shall promptly organize emergency repair, notify the water use units and individuals, and report to the administrative department of urban water supply and water use. Emergency repair for more than 24 hours still can not restore water supply, emergency water supply measures should be taken. Article 14 When the normal water supply is affected due to natural disasters, emergencies and other special reasons, if the urban water supply unit cannot give advance notice, it shall promptly notify water users and individuals at the same time of emergency repair, and take necessary water supply dispatching and engineering measures to give priority to ensuring residents' basic living water. Fifteenth urban water supply and water administrative departments shall prepare an emergency plan for urban water supply emergencies, and report it to the people's government at the same level for approval before implementation, and submit it to the emergency management department at the same level and the administrative department of urban water supply and water at the next higher level for the record.

Urban public water supply units shall formulate corresponding emergency plans for urban public water supply emergencies, report them to the administrative departments of urban water supply and water use at the same level for the record, and organize regular drills.