Summary of hydropower supervision work
Summary model essay of hydropower supervision work

Summary is to review and analyze a certain period, a certain project or a certain work afterwards, so as to draw regular conclusions. Through it, we can correctly understand the advantages and disadvantages of previous study and work. Let's write a summary for ourselves. How should I write a summary? The following is my carefully compiled summary essay on hydropower supervision, which is for reference only and I hope it will help you.

Summary of the model essay on hydropower supervision 1 The time cursor began in July of xx, and I walked on the high arch of Xiaowan along its direction. I am not its builder, nor a participant who only sticks to his own trademark, but an admirer of it. It is my idol, so learn from it and pay tribute to it! And this is Xiaowan, Gao Gongba, leader, big brother and colleague. Thank you for your concern, support, help, guidance and management. Say, a person's future does not come out by himself, but you come to the right fork in the road, and the right person smiles and says to you: This way. And this, you in the small bay, may be the person who can still laugh in retrospect after many years. Thanks again for your smile!

Xx is the decisive battle year and the harvest year of Xiaowan Hydropower Project's ten-year construction. Although we can't feel the pride of the creator, we can feel the joy and luck as a member of the power plant. Although we know very little, we are learning. Although what we do is very simple, we are working hard and practicing. Through various training and study reports in factory education, I have a preliminary understanding and understanding of Lancang River Company and Xiaowan Project. Through the study of safety knowledge, we learned how to protect ourselves and others at work, understood the hazards on the construction site, enhanced the significance of safety and prevention, and always reminded ourselves: people, this is a beautiful life, and life is more important. I have not only my own life in my pocket, but also the happy life of others. Department safety training and practical training We should be careful in our work. Safety is not the only thing. In any work, we must care about others and ourselves and work as hard as we cherish life.

The learning of engineering knowledge lies in practice, and those abstract drawings, concepts and data can only be embodied through practical learning! With the guidance and help of the master of the Safety Supervision Department of the Construction Management Bureau, I saw that I learned a lot of construction methods and quality evaluation standards of Xiaowan Project, and also learned a lot of essential experiences and methods in my work. The construction method, details and problems that should be paid attention to during the maintenance of the anti-impact and wear-resistant concrete in the spillway tunnel are not so abstract; The understanding of the faucet is no longer just its benefits, but also the construction difficulties caused by inclination; The causes of concrete pits and honeycombs, the obvious difference between insufficient or excessive vibration and concrete quality leakage; Xiaowan's "four highs" have specific concepts, and he also understands and laments the concept of billions! Of course, it is more important to learn and understand the methods in engineering practice, the problems that should be paid attention to, and have a certain understanding and understanding of various concepts of engineering, so as to get exercise from learning and practice.

After several months of training, study and practice, I have learned a lot of knowledge and truth, and also exercised myself in my life and work. But there are still many shortcomings, which need us to continue to study and practice. In the future work, we should communicate and share more with colleagues, go to the construction site and practice more, and also need the help and guidance of all brothers and sisters.

Summary of hydropower supervision: 20xx years have passed and ushered in 20xx years. In the past year, I participated in the construction of the Oak Bay project. High-rise buildings have sprung up in the mire of unfinished projects. In this process, we have fully fulfilled our construction project supervision obligations entrusted by laws and regulations. We have carried out the whole process supervision in the contractors, construction parties, material suppliers and other participating units, and the project quality and safety are accident-free. Looking back on the regulatory work in the past year, we can make the following summary:

A, project engineering and project supervision institutions

Oak Bay Project has two general contractors (China Construction Third Bureau and Jiangsu Shuanglou), both of which are national first-class construction enterprises. The general contractor and the construction section are divided into two construction blocks, and the project supervision organization is divided into two supervision groups. I am a professional supervision engineer in the supervision team of the Second Bid Section (Jiangsu Shuanglou Bid Section), and there are three others. The four-person supervision team will supervise the construction of six buildings and their gardens in this bid section, and the chief supervision engineer will appoint me as the leader of the supervision team.

Second, the feeling of working this year

1. Correct attitude and clear thinking.

20xx came to Oak Bay Project on February 26th. Since I entered the supervision work of this project, I have been helped by the chief supervision engineer and some supervisors. In addition, I am deeply stressed and have the following concerns: the supervised unit is a national super-class enterprise. Although I have supervised such construction enterprises, I was not in charge at that time, nor was I a first-class project. Later, with the help of the director, the idea of "observing the law, being scientific, actively and seriously supervising and serving the construction unit" was established. In every season, everything at work, words and deeds and arguments are based on this. Six words have always been in my heart, namely "company, responsibility and consequences".

2. Coordinating internal and external relations is the key work for supervisors to create a working interpersonal environment.

In one year's supervision work, from the inside (within the supervision team) to the outside (the supervised unit), there are often differences, even quarrels, or other unpleasant phenomena for both sides. In this regard, my leading thought is "people are not sentient beings." Everyone walks together for work, regardless of age, culture or skill. They should respect each other and treat each other as equals. They must never be arrogant or supercilious, let alone talk about others behind their backs. I hate people who are hairy and call others monsters. I respect anyone and try to unite all those who can be United. If I meet the kind of person I hate, I have to stay away. In the implementation of supervision work this year, unpleasant phenomena have occurred in our supervision team one after another. I used to think that I was just a special supervisor. Although the director called me the leader of the supervision team, it only played the role of "representative", which may have certain significance in the supervision of the project, but it has no significance among the internal personnel. Besides, they have been in the leadership for a long time and communicated more than me, but I firmly believe that my favorite leader will not. Later (in the second half of the year), the relationship gradually became harmonious. Although they don't report to each other and communicate with each other, they go their separate ways, and I don't ask more questions on idle days.

In engineering supervision, most of them are dealing with people. Theoretically, although they practice along the track of laws and regulations, it is the key to find feelings, realize truth and adopt appropriate methods to achieve their goals among the people involved in the work. Supervision engineer and supervision unit, construction unit and management personnel of construction project department are the relationship between supervisor and supervised. We are also a fair and just party among the three subjects of construction projects, and they are equal. Supervisors should not be arrogant in front of construction units and individuals, but should convince people by reasoning and communicate with each other in a peaceful manner, which involves structural safety, construction safety, use function and the interests of construction units. The speech art of conversation is a hierarchy, and it is the only way to solve the problem peacefully to achieve "rigidity in softness, softness in rigidity". I deeply feel that the saying "a word makes people laugh, a word makes people jump" is good, which has two kinds: grammar, tone and result. In the past year, my working relationship and personal relationship with the construction party have never been tense. In my daily work, I pay attention to working methods and language art, and also adopt a combination of "strictness" and "looseness" and "rationality" and "style". While ensuring the safety of engineering structure, use function and construction, I can flexibly exercise the rights of supervision engineers and do a good job of supervision without harming the interests of the construction unit.

Maintaining a close working relationship with the management personnel of the construction unit is the primary work of supervision, and it is also a necessary condition for the supervision unit to fulfill the supervision contract and establish the image of "integrity" in the construction unit and the construction market. Although the Oak Bay Project has implemented project supervision, due to the large number of sub-projects and units contracted in parallel, the construction unit has also established a quality, schedule, cost and contract management system to participate in on-site management. In this case, we supervise how to do a good job, fulfill the work obligations in a timely and comprehensive manner, not neglect their duties, satisfy the construction unit, and prevent the supervision company from leaving any negative impact on this project. I reflected on this, and under the guidance of the chief supervision engineer and my own consciousness, I decided to carry out my work with the method and attitude of "initiative, cooperation, communication and exchange". I usually communicate with the representatives of the construction unit with my own clear views and form a written document when necessary. I am the head of this supervision team. When finding or feeling that the project quality or management is uncomfortable and there are new trends in the quality progress, actively communicate with the production general manager of the engineering department, clarify the work objectives, clarify the work ideas, and make its supervision work change from passive to active.

Third, lack of self-feeling and personal plans for next year.

1994 my lack of self-feeling in supervision work has three aspects: one is emotional instability; Second, in some periods, work cannot be systematically and carefully considered and arranged, and neglected places are often remembered when others talk about it or are outdated; Third, the professional technology is not comprehensive, and the construction technology and quality acceptance standards of some sub-projects are not familiar enough. Although I have been familiar with most of the books and online for a year, I am still not sure, especially in the process of accepting, I forgot some accepted contents, and then I remembered to go back and read them again. As for emotional instability, it is mainly manifested in getting angry when encountering something different and unreasonable, and there is something wrong with speaking attitude.

19 14 years, with the support of company leaders, I passed the provincial registered supervision engineer, which was a great encouragement to me. I am determined to make persistent efforts in the supervision work next year, improve myself better and do a good job in supervision. Carry forward the heroic spirit of "promoting my honor and restraining my shame", and be responsible to the chief supervision engineer and his own supervision company for everything he does in his work; Strive to improve professional skills and supervision level, and become a compound, qualified and advanced engineering supervision worker.

In addition, some suggestions for this supervision company.

At the internal meeting of project directors on 19 141February 3 1, Mr. Liang made clear to us the personnel changes of the company's leadership and announced the new leadership team, which made me see hope and strengthened my confidence in continuing to do a good job in the company. Here, I would like to give some suggestions to the company for the leaders' consideration:

1. Set up an inspection team in the company to carry out regular and irregular inspections on all project supervision institutions and their personnel belonging to the company, and inspect, evaluate and publicly evaluate the implementation of the work system, project entity quality, supervision data, quality assurance data, safety data and technical data of the project supervision institutions and their personnel, and even reward them;

2. At the same time, the inspection team will pay a return visit to the evaluation opinions of the construction unit on the supervision work of the supervision institution and its personnel one by one, and ask the construction unit to evaluate the supervision institution (even the supervision personnel) in the evaluation form drawn up by the company as a reference for the year-end joint remuneration.

3. Establish and improve the personnel management system, the combination of labor and remuneration system, benefit sharing system and fault punishment system, and form a unique enterprise management culture. Punish or ban those who have the ability not to play, are not pragmatic, are corrupt in professional ethics, are mercenary and leave oil behind; Demote those incompetent personnel and form a strong supervision team.

4. The chief supervision engineer shall implement the responsibility system, and reward and punish the assessed supervision institutions, and the amount of rewards and punishments shall be led by the director.

All the above are true and should be reported to the company leaders. If there are any mistakes or shortcomings, please criticize and correct them.

A summary of the model essay on hydropower supervision 3 I. General situation of the project

This project is located in Fuhui Road, Gucheng District, Lijiang City, Yunnan Province, with a building area of 2,446 ㎡ and a three-story frame structure. The partition wall is mainly light steel keel double-layer gypsum board, some of which are glass, and the wall surface is generally plastered with latex paint. The floor of the main passage is floor tile, and the floor of the room is self-leveling PVC floor. The bathroom wall and floor are ceramic tiles, and the counters and countertops are artificial stones, which are spliced on site. The ceiling of the lobby and some offices on the first floor is made of mineral wool board and gypsum board, and there is no ceiling in the workshop and conference room, which is painted uniformly.

Second, the supervision personnel configuration

According to the supervision contract and supervision specifications, combined with the actual construction situation of this project, the resident supervisor stationed at the site is Deng Kai.

Third, the performance of the supervision contract

According to the entrusted supervision contract, design documents, current national construction specifications, quality inspection and evaluation standards, and related standard atlas, the project supervision department carried out in an orderly manner and fulfilled the contractual obligations and responsibilities in combination with the requirements of project supervision planning and supervision outline.

1. Supervision time: September 8, 20xx to February 3, 20xx for completion and acceptance.

2. According to the engineering situation and supervision scope, a series of supervision systems, such as site meeting system, witness sampling system of main equipment and materials, re-examination and inspection system of sample delivery, and on-site supervision system, have been implemented.

Concealed engineering acceptance system, disciplines, division of engineering quality inspection system, engineering data audit system, etc.

3. Through the combination of patrol supervision and on-site supervision, the project construction is under control.

4, take the initiative to do a good job in precontrol (such as drawing approval, technical disclosure, etc.). ), strengthen process control (such as floor tile installation inspection, etc. ), and actively take post-event control measures (such as repair and inspection of engineering quality defects, etc.). ) to ensure the quality and progress of engineering construction.

5. Actively assist the owner to pay special attention to the construction progress, carefully review the construction progress plan, compare the actual construction progress with the planned progress in time, and urge the contractor to pay close attention to the construction progress.

6. Carefully verify the actual completed quantities, review the application for payment of the construction project, and control the project cost.

7. Inspect and supervise civilized and safe construction, assist the management personnel of the construction party to educate the operators about safety in production, improve the awareness of safe construction, and achieve safe and civilized construction.

Four, the main supervision work and results

1, according to the design drawings, construction acceptance specifications and standard atlas, the construction organization design and construction scheme approved by the supervisor, combined with the project supervision planning, the construction quality is monitored in real time by means of patrol, standing by and parallel inspection. Explain the construction procedure, design basis and working principle to all parties; Through communication, the relevant personnel of all parties can make clear the quality, control content, inspection points and how to operate of each sub-project and sub-project construction (including working procedure), which effectively ensures the work quality of the supervision department.

2. Before the construction of major disciplines, divisions or major working procedures, make technical disclosure with the contractor, and give oral instructions directly to the construction section level when necessary. Make the management personnel at all levels of the construction party clear about the key quality control contents that should be paid attention to in the construction of this sub-project, division and main working procedure, so as to take measures for pre-control as soon as possible.

3. Read the construction drawing carefully, understand the design intent, urge the construction party to declare the construction changes that are beneficial to the owner, and try to solve the mistakes and omissions in the construction drawing before construction.

4. Check the integrity of the mechanical equipment that comes into play, whether it can run safely, and go through the inspection formalities of the equipment in time after meeting the requirements. When the air compressor, cutting machine and other equipment run for a period of time, remind the construction party to check, replace and oil the equipment parts in time to ensure the construction safety.

5. Review the warranty information and check the appearance quality of the main materials entering the site. After meeting the requirements, witness sampling and parallel inspection shall be carried out in accordance with the regulations, and inspection shall be carried out after the second interview to ensure that qualified materials are used in the project.

6. Carefully check the elevation of the axis and each structural layer to ensure the accuracy of the setting-out of the decoration project.

7. Carefully check the production and installation quality of artificial stone counters in the lobby on the first floor, focusing on the construction of splicing and polishing to eliminate joints. Ensure that the manufacturing and installation meet the requirements of design and construction specifications.

8. Stand by to supervise the construction of dry-hung granite stone in the lobby on the first floor, and supervise the whole construction of corner columns and other parts that are not easy to hang but are positioned with expansion bolts on site to ensure the construction quality and safety.

9. Patrol and supervise the construction of light steel keel gypsum board partition wall. Frequent random sampling and parallel inspection are carried out for the filling location of silencing cotton and the spacing of light steel keel to ensure that the design quality requirements are met.

10, check the plastering types in time during the decoration project construction to ensure that the mortar varieties meet the design requirements. Always check whether the plastering surface is smooth and smooth, and whether there are any quality defects such as delamination, hollowing, ash explosion and cracks. Exterior wall plastering emphasizes layered leveling. Remind the construction party that the wall behind the pipeline and the plastering around the floor through which the pipeline passes should be in place. Internal wall construction quality check whether its surface is smooth, powdery and peeling, so that the construction quality meets the requirements and the overall decoration effect is ideal.

1 1, timely supervise and audit the construction unit to sort out the construction technical data, so as to synchronize the arrangement of construction data with the progress of the project and ensure that the disciplines, the main body and the completion acceptance can be carried out in time.

12, hydropower supervision:

(1), first of all, the qualification of installation and construction personnel shall be reviewed and required to hold relevant certificates.

(2) For the concealed works such as pipeline embedment and reserved hole position on the floor, the supervisor should first review the concealed works data provided by the construction unit, and then go to the site for inspection and acceptance according to the requirements of drawings and specifications.

(3), in the process of installation, on-site inspection at any time, found that the problem is pointed out in time and rectification. Whether the grounding device meets the design and construction specifications, whether the elbow of the concealed pipeline meets the requirements, and whether the slope inspection port and expansion joint of the pipeline are constructed according to the design and construction specifications.

(4) After the self-inspection by the construction unit, the supervisor shall inspect the installed sectional works according to the engineering quality acceptance specifications and evaluation standards.

(5), take cover engineering, all kinds of tests, after the test, apply for a visa to the supervisor in time.

Problems and solutions of verbs (abbreviation of verb)

1, the design drawings are inconsistent with the actual situation on site, and there is a lack of on-site design representatives. On-site supervision engineer communicates with the design by telephone for rectification.

2. Because there are many partitions in this project, there are many joints between old and new walls; In plastering construction, horizontal cracks in different degrees appear at the junction of partition wall and beam bottom. No cracks were found after technical treatment.

Ending of intransitive verbs

The implementation of this project supervision has been strongly supported by the owner. During the construction of the project, the relevant leaders of the owner's unit and the resident personnel cooperated with the supervisor for many times to monitor the quality and progress. Relevant personnel often patrol the construction site and put forward positive suggestions and requirements for the quality control of some key parts and key processes, which played an important role in ensuring the quality of the project. Express my heartfelt thanks to you!

;