2. The self-use electricity of distributed photovoltaic power generation system is exempted from various funds and surcharges levied with the electricity price, as well as the system reserve capacity fee and other related grid-connected service fees.
(3) Subsidize the electricity bill. Power grid enterprises shall, according to the user's meter reading cycle, measure the power generation, on-grid electricity and spontaneous self-use electricity listed in the subsidy catalogue of distributed photovoltaic power generation projects as the basis for calculating subsidies.
(4) disbursement of funds. According to the additional income of renewable energy price and the estimated power generation of distributed photovoltaic power generation projects, the central government allocates subsidy funds to State Grid Corporation of China on a quarterly basis. Power grid enterprises shall timely pay subsidy funds according to the project power generation, the subsidy standards determined by the state and the settlement cycle of electricity charges.
After the end of the year 1 month, State Grid Corporation shall liquidate the subsidy funds of the previous year for the projects within its business scope, and report them to the Ministry of Finance, the National Development and Reform Commission and the National Energy Administration after the approval of the provincial finance, price and energy authorities. The Ministry of Finance shall jointly review with the National Development and Reform Commission and the National Energy Administration.
The main contents of the distributed photovoltaic electricity price subsidy include: all distributed photovoltaic power generation projects, including spontaneous self-use and surplus electricity on the Internet, can get a subsidy of 0.4-0.6 yuan/kWh. On October 26th, 2065438+0165438/KLOC-0, the National Energy Administration issued the Interim Measures for the Supervision of Photovoltaic Power Generation Operation, which is valid for three years. It is stipulated that power grid enterprises should fully purchase the grid-connected photovoltaic power station projects and distributed photovoltaic power generation projects within their power grid coverage, and clarify the supervisory responsibilities of energy authorities and their dispatched institutions for grid-connected photovoltaic power generation operation, as well as the responsibilities that photovoltaic power generation project operators and power grid enterprises should bear, which promotes the orderly grid-connected photovoltaic power generation.
Legal basis: Interim Measures for the Supervision of Photovoltaic Power Generation Operation
Article 6 The competent department of energy in the State Council and its dispatched offices shall supervise the power quality of photovoltaic power generation in accordance with relevant regulations.
The power quality of photovoltaic power grid should meet the national standards to ensure the reliable operation of the grid.
Seventh the State Council energy authorities and their agencies to supervise the construction of photovoltaic power grid.
Photovoltaic power generation projects connected to the public power grid, access system engineering and public power grid transformation caused by access shall be invested and constructed by power grid enterprises. Access to the photovoltaic power generation project on the user side, the access system project is invested and constructed by the project operator, and the public power grid transformation caused by access is invested and constructed by the power grid enterprise.
Article 8 The competent energy department of the State Council and its dispatched offices shall supervise the grid-connected photovoltaic power generation services.
Power grid enterprises shall, in accordance with the principle of active service, simplicity and high efficiency, establish and improve the grid-connected service process of photovoltaic power plant projects, and provide services such as grid-connected process description, relevant policy explanation, grid-connected progress inquiry and coordination with grid-connected commissioning and acceptance.
Power grid enterprises should provide convenient conditions for distributed photovoltaic power generation access, and simplify the procedures for the whole process of grid-connected application acceptance, access system scheme formulation, contract agreement signing, grid-connected acceptance and grid-connected debugging in accordance with the principle of "one mouth is external".
Power grid enterprises are exempt from system reserve capacity fees and related service fees for distributed photovoltaic power generation projects.
Ninth the State Council energy authorities and their agencies to supervise the time limit of photovoltaic power grid-connected links.
The time limit for grid connection of photovoltaic power plant projects shall be implemented in accordance with the relevant provisions of the National Energy Administration.
For distributed photovoltaic power generation projects, power grid enterprises shall provide access system solutions to the project owners within 25 working days from the date of accepting the application for grid connection; Within 5 working days after the project owner confirms the access system scheme, the project owner shall provide opinions on access to the power grid, and carry out follow-up work such as project filing and engineering design accordingly; After accepting the application for grid-connected acceptance and grid-connected debugging, complete the installation service of the gateway electric energy metering device within 10 working days, and sign the power purchase and sales contract and grid-connected agreement with the project owner as required; Organize grid-connected acceptance and grid-connected debugging within 10 working days after the installation of the gateway electric energy metering device, and provide acceptance opinions to the project owner. Directly connected to the grid after commissioning, and the acceptance standard shall be implemented in accordance with relevant state regulations. If the acceptance is unqualified, the power grid enterprise shall propose a solution to the project owner.