Hello, what materials and procedures do you need for the rooftop photovoltaic project in Dongguan? Details, looking forward to your reply, thank you!
1. The owner of the low-voltage residential photovoltaic power generation filing project prepares the filing materials and submits them to the power supply department, which, on behalf of the residential customers, centrally files them with the local energy authorities. The following information should be provided:

(1) Basic information of the project: including project name, construction address, construction scale, construction conditions, engineering technical scheme, implementation scheme, economic evaluation, etc.

(2) Credit certificate of the project owner: identity information of the project owner;

(3) proof of funds;

(4) Legitimacy certificates of buildings and facilities on which the project depends: such as real estate license; When the owners of the buildings, sites and facilities that the project unit relies on are not the same subject, it is also necessary to provide the use or lease agreement of the buildings, sites and facilities signed by the project unit and the owners.

2. Non-resident projects are compiled by the owners themselves: (1) Basic information of the project: including project name, construction address, construction scale, construction conditions, engineering technical scheme, implementation scheme, economic evaluation, etc. ; (2) Credit certificate of the project owner: enterprise business license, organization code certificate, etc. ; (3) proof of funds; (4) Legitimacy certificates of buildings and facilities on which the project depends: such as real estate license; When the owners of the buildings, sites and facilities that the project unit relies on are not the same subject, it is also necessary to provide information on the use or lease agreement of the buildings, sites and facilities signed by the project unit and the owners, and report it to the local energy authorities (Electric Power Department of the National Development and Reform Commission) for the record.

I hope our answer can help you. If you have any other power supply problems, please feel free to call the power supply hotline 95598 for consultation.