Structural engineer becomes a full member and summarizes personal summary. A xx project started construction in the middle of X month in xx year, in which the total area of portal steel structure in pipe-making workshop is 9820m2, and the total area of portal steel structure in reserved warehouse is 3840m2. The main body was put into use at the beginning of X month in xx year and in the middle of X month in xx year respectively. This achievement can not be achieved without the correct leadership of the company and the hard work of all the staff in the project department, and it is also the result of the unity and cooperation of our design department, ministry of materials and equipment, Engineering Department and other companies. In the whole construction process of the project, we also deeply realize the importance of teamwork, some of our own shortcomings, team harmony and so on are the key factors that affect the smooth progress of the project. Therefore, the engineering work is summarized as follows:
I. Time limit for a project
In the early stage of project construction, with the joint efforts of the whole company, the overall operation was good, and the project showed a good trend in terms of safety, quality and progress, but raw material processing was an important link. Therefore, in the process of materials entering the site, the audit and acceptance of materials are related to the safety and progress of the project. (Material FAQ: 1. The material is inconsistent with the original drawing. Check one by one with reference to drawings to ensure the correctness of materials; Secondly, in the process of raw material processing and production, the company strengthened supervision to ensure the correct production of materials and unnecessary troubles in the later period. 2. The corresponding information of raw materials entering the site is not perfect. It is suggested that in the process of distributing materials, the corresponding information personnel should be organized to prepare the corresponding materials for distribution with the vehicle. 3. Do a good job of the blue prints.the design. The common sense of the original drawing design may sometimes conflict with the on-site installation and production, which will lead to the later on-site changes and delay the work. In view of the above, it is hoped that before the construction site starts, the corresponding leaders of the company, the design department, ministry of materials and equipment and the engineering department (it is suggested that the construction team meet when conditions permit) will be convened to hold a "pre-work meeting" to make overall plans for drawings, contracts, raw material acquisition and material distribution.
In foundation construction, weather and other irresistible factors are the biggest stumbling block that affects the smooth completion of the whole project. Therefore, the site management personnel should make corresponding adjustments according to the actual situation, Party A, weather and other factors, reasonably arrange the construction progress, and formulate practical and effective measures to catch up with the progress. Here, I also deeply realize my own shortcomings. In the face of rainy weather, I can't reasonably arrange workers to prepare for the later project progress, which leads to a corresponding extension of the construction period when conditions permit. When the progress of the project is accelerated, it is also my own management experience to rush to meet the construction period, which can not be completely reasonable and effective, so there are many places to learn in the future work.
Second, the engineering construction safety
On-site construction should truly realize that safe production is the premise and guarantee for enterprises and individuals to cast Zotye fine products. Can understand the social attitude of "people-oriented, safety first" and the importance and necessity of safety facilities investment, safety education and prevention. In the early stage of the project, do a good job in workers' safety education, sign the corresponding labor contract, make safety disclosure, and always keep in mind the safety awareness. As the person in charge of the site, I have an unshirkable responsibility to take corresponding emergency measures with the cooperation of Qi Xin, the leader of the company, to win the most precious rescue time for the injured in time and effectively. It provides a strong guarantee for the final health recovery of workers. So I also deeply reflect on myself and remember my mistakes. In the future construction site safety management, I will always focus on "three treasures, four mouths and five boundaries", on-site civilized construction, workers' safety education and investigation of potential safety hazards, and formulate specific safety implementation plans and measures to ensure the smooth progress of the project.
Third, the quality of engineering construction
A century-long plan, quality-oriented. Xx project has been completed, but there are still many thorny problems, such as water leakage at the joint of sunshine brick on the roof panel, water leakage in the window on the wall, etc ... which really affected Party A's production and caused unnecessary losses to the company. I feel deeply guilty about this and have been working hard to fix it. In view of the above, I think that in the process of engineering construction, we should always supervise its construction procedures to avoid workers being careless. Sign a technical disclosure with the operation team, sign a quality agreement if necessary, and formulate the corresponding quality inspection cycle, so that the quality defects found in the construction process can be solved and the quality problems can be truly within the dynamic management of quality inspection. In strict accordance with national norms, standards and household acceptance standards, quality implementation.
Fourth, cost control and project advance payment
1, cost control
1) material control: detailed construction budget and material consumption plan were made at the initial stage of construction, and gradually improved according to the changes of site conditions, design changes, negotiations and other factors during construction. Each construction team picks up materials according to the task list, and the materials entering and leaving the warehouse are recorded in detail. Under the condition of ensuring the normal supply of materials, eliminate waste.
2) Adopt new technology to reduce labor consumption, improve efficiency and increase benefits.
2, the project advance payment
The advance payment clause in the construction contract signed with xx Group Co., Ltd. has been delayed and delayed by the construction unit, which has also affected the smooth progress of the project to some extent. In view of this problem, the site manager should communicate with Party A as soon as possible to ensure payment and make the most practical and powerful backup guarantee for the company.
We have never defaulted on the labor contract signed with each operation team according to the contract. Although there are occasional delays, we have tried our best to do a good job of appeasement at the scene to ensure that migrant workers can finally work safely and go home happily.
Looking back on this year's work, we have both growth and shortcomings. We should clearly analyze the shortcomings and advantages in our work, understand the gap, accept the experience, draw lessons, foster strengths and avoid weaknesses in future work, and improve and improve the construction methods, which are valuable assets for future work. In the future, I will gradually improve my point of view and consciousness, constantly improve my professional quality and level, strengthen my sense of responsibility, cultivate the spirit of love and dedication, be people-oriented, strengthen management and enhance the spirit of teamwork. Let the achievement of our engineering department be verified as "brilliant xx, showing the elegance of Tiejun".
The structural engineer became a full member and summarized my personal summary. In xx, I had the honor to join xx Co., Ltd. and become a structural designer in R&D department. With the care and support of leaders, with the help of all my colleagues and friends, through their unremitting pursuit and efforts, I have been trained and improved in professional skills and work.
In the past year, my main task was to design the structure of oxygen analyzer. In the past year, four models of oxygen analyzer have been produced, namely sst model, volks model, PhD model and electrochemical model. In the process from proofing to testing to production, structural problems are found and solved in time, which makes the product structure more perfect and also reflects the simplicity of installation, disassembly and maintenance in production. At the same time, I also participated in other projects, such as the design of sealing device in test room, the improved structural design of gas filling device, the manufacture of flue gas light source, the gas filling ratio experiment of four-component flue gas analyzer co and co2, the partial structural design of two-way flue gas analyzer and the assembly of the whole machine.
In the above work, I summed up that as a structural designer, we should carefully and meticulously combine the reality and proceed from the reality to realize the design requirements. I am also good at finding problems, summing up problems and avoiding the same problems in secondary development. Of course, if we do this, there will be no problem. For example, in the proofing of structural drawings, there must be reviewers before drawing, and it may be difficult to find problems by drawing on our own. If there is a reviewer, it can avoid the mistakes of proofing products caused by drawing errors, and also change the completion of proofing and shorten the proofing cycle.
Xx years, I just entered the design industry, and now I know and recognize this industry. I saw the results of my own efforts and my own shortcomings. So in the new year, I decided to combine my own reality and the company's overall strategy to formulate my own work and study goals, so as to better complete the design tasks and improve my comprehensive ability. Seriously study norms, norms are the basis of design, so I intend to study norms seriously in xx years to achieve the goal of being familiar with commonly used norms and being able to recite some mandatory terms and apply them in design. Secondly, master the basic design modeling. Furthermore, in terms of design tasks, combined with the company's overall development strategy, we can better complete the structural design of the project and better realize our own values and goals.
Structural engineer becomes a full member and summarizes personal summary. Due to the manpower deployment of the three companies, I was transferred from xx project to xx project as a civil engineer in X month of 20xx. With the help and guidance of General Manager xx and other project colleagues, I tried my best to do my job well. Now I will briefly summarize my work and study in the past year as follows:
I. Description of work situation
I am responsible for the project management, handover and maintenance of xx building in xx District from xx to X, and for the project management of xx building from X to X.
Second, clear job responsibilities.
1. Perform supervision duties: be responsible for the acceptance of engineering divisions, disciplines and inspection lots; Responsible for compiling and summarizing project supervision logs and supervision data; Conduct a comprehensive inspection of the key construction parts of the site and the station, report the quality and safety problems to the director in time, and take corresponding solutions.
2. Perform Party A's duties: be responsible for on-site quality management, and collect, sort out and save data management materials. Responsible for auditing budget, settlement, construction organization design, various construction schemes, material plans, on-site visas, design changes, etc. Responsible for on-site communication and written data transmission with the company and design institute on matters such as joint review of drawings, design change, slot inspection and subject acceptance. Responsible for coordinating the construction problems of the general contractor and subcontractors.
Third, the daily work situation
1.During the construction of Building X in Zone X from October to October, the main responsibility is to check the labor and material installation on site and report to the leader regularly every day. If quality problems are found, the Fourth Bureau is required to make timely rectification and report to the leaders. Coordinate the construction problems of subcontractors and general contractors. Responsible for household acceptance and handover before property delivery.
2. During the hardcover construction of xx building in X area from X month to X month, I was mainly responsible for the design change of the construction model room of xx building, conveying the relevant technical requirements of the company to xx and xx hardcover units, and being responsible for the audit and reporting of the bathroom waterproof scheme and ceiling scheme. Responsible for the division, disciplines and inspection lot acceptance of two buildings. Be responsible for confirming the structural problems and quantity of the original construction unit on site. Responsible for communicating with designers about drawings. Responsible for Party A's subcontracting material plan. Responsible for the compilation and summary of supervision log in X project area.
3. During the hardcover construction of Building X 1xx since X month, it is mainly responsible for the audit of construction organization design, the budget audit of steel clips of the Fourth Bureau and the report of quantities. Responsible for contacting designers to prepare valuable drawings. Responsible for the acceptance of ceiling keel, waterproof construction, kitchen and bathroom tiling, facade insulation and wall plastering on the construction site. Responsible for the compilation and summary of supervision log in X project area.
Fourth, the results of the work
1, Building X, Zone X, was delivered to the owner from X to X. At that time, 73 owners came to repossess the building, and 69 owners have repossessed the building. At that time, the repossession rate reached 95%. The owner has no major complaints.
2. Current progress of the physical model room in Area X: Except bathroom hardware, wallpaper and water cabinet, other sub-projects have been completed.
3. Construction progress of xx building in X area: wall putty is completed at one time, wood keel with wood veneer is completed, ceiling keel is completed, and waterproof layer is 4~ 16 (16~ 10 after acceptance). Kitchen bricklaying 16~4 floors, bathroom bricklaying 16~ 15 floors, ground cushion completed, facade insulation completed, real stone paint 30%, aluminum window glass fixed installation 80%, external elevator removed, fire fighting 16~9 floors, and two indoor elevators installed.
4. The examination and approval of Loft waterproof scheme, ceiling scheme and construction organization design scheme in 4.xx area is completed; Synchronization of construction data and progress, and synchronization of supervision logs and station records with construction progress; Due to the need of joint review of drawings, the project budget entrustment of steel clips has not been changed, and design changes are being coordinated and distributed.
5. The preparation work for materials of Building A, B and A in Zone X has been completed to meet the subsequent construction progress.
Verb (abbreviation of verb) experience summary
1, found insufficient.
(1) Combined with the quality problems of project quality in Area X, the problems such as cracks in the attic ceiling, water leakage in the bathroom, moldy wallpaper, and alkali flooding in the bathroom stone were avoided in the construction of Area X. ..
(2) On the progress of the project, the construction unit in Area X was replaced by hardcover, and the production and construction of xx and xx were on the right track. Due to the arrears of project payment, the material supplier failed to provide construction materials in time, and there were too many quality problems in xx construction, which led to the delay in delivery.
(3) Shortboard of safe and civilized construction: The garbage in Area X is not cleaned in time, and there are potential safety hazards in site construction.
2. Corrective measures
(1) The problem of ceiling cracking has been communicated. Double plasterboard is used in the design, and reinforcement measures are taken for weak parts. The problem of toilet leakage has required the construction unit to report the scheme separately. In the cushion construction, steel wire mesh is used to strengthen the wall root, and the buried pipe construction is strictly required to avoid the brick sticking error caused by ultra-high buried pipe. When the waterproof construction is accepted, notify the regional engineer to carry out multi-party acceptance of the project, and strictly require the waterproof thickness and height; In the process of sticking bricks, the project engineer is required to stand by and avoid damaging the waterproof layer. The problem of uneven wallpaper requires strict acceptance of wall foundation construction. The problem of stone flashing requires you to strictly control the materials entering the site.
(2) On the schedule, you are required to inspect the site every day, and coordinate the construction unit in time and report to the leader when you find the shortage of materials and labor.
(3) In terms of safe and civilized construction, you are required to patrol the site more than twice a day, and ask the construction unit to rectify and report to the leader in time when problems are found.
Intransitive verb 20xx work plan
1, construction progress plan
(1) The ceiling sealing plate, aluminum window glass installation, lobby and the last floor are basically perfect, and the indoor elevator is completed in xx building in X area of 20xx month.
(2) The organization of xx building in X area in 20xx month was completed, and the real stone paint on the facade was perfect. Indoor putty, waterproof, bricklaying, stair railing, wood veneer, door installation and fire door installation are completed.
(3) The first floor of xx building in X area in 3)20xx month was fully resumed, with 60% wallpaper, 80% indoor door installation and lamps completed. 50% radiator installation, 50% cabinet installation and 50% shower glass installation.
(4) Complete the installation of range hoods, gas stoves, water heaters, shower glass, bathroom hardware, wallpaper and wood floors in xx building, X district, X month, 20xx.
(5) Building 5)20xx, X, X, X, xx, household acceptance, property handover and delivery to the owner.
Seven. Expectations of the company
1. The letters sent by the general contractor and subcontractors reflect that the financial pressure is so great that the work of the project department cannot be fully promoted. The project suggests that the company can pay the project cost of the approved output value in full.
2. It is suggested that the company regularly provide professional training for project engineers.
3. I hope the company can raise the salary according to the personal work situation.
Structural engineer's formal summary personal summary 4. I officially went to work in the company on xx, XX, XX. Today, the three-month probation period has passed. During these three months, with the care of leaders and the help of colleagues, relying on my professional foundation and work experience, coupled with hard study and study, I quickly adapted to the working environment and successfully completed the tasks assigned to me. This work is briefly described as follows:
First of all, personal introduction.
Xx years x months -xx years x months, studying xx major in xx University; From xx to the end of xx, I worked in XX Gas Thermal Planning and Design Institute for gas thermal design; I have been working in the company since the end of xx.
Participated in and passed the national registered public equipment engineer (electric power) qualification examination (basic subject) in xx years and X months; Participated in and passed the qualification examination (basic subject) of national registered utility engineer (HVAC) in xx years and X months.
Second, the work performance during the probation period
1, strictly abide by the company's rules and regulations. At the beginning of my work, I carefully studied the company's attendance and other rules and regulations, and kept them in mind, always reminding myself to strictly abide by the company's rules and regulations and maintain the company's image. If I insist on coming to work early every day, I will always remind myself that I represent the image of the company and pay attention to my words and deeds.
2. According to my major, my job is to design electric power and HVAC. According to the arrangement of the leader, I have been in contact with the projects of Asia Aluminum since the day I went to work. Under the guidance of Mr. Zhang, I am mainly engaged in the power design of this project, mainly including the pressure pipeline design of compressed air, industrial gas, steam, natural gas and other gases. I have never been exposed to such a project before. This project is brand new to me, not only in knowledge but also in form. The method of doing things is completely different from the previous work, and I suddenly feel unprecedented pressure and urgency. On the premise of not disturbing Zhang's work, I will ask him as much as possible, and of course I will give priority to self-study. Between work, I consult all kinds of materials and keep learning compressed air and industrial gas in order to work better. This project of Alcoa tests whether my knowledge is suitable for this job from all aspects, including language, because all the information provided by the owner is in English, which makes me have to improve my English. At work, I consult reference books to help me understand. After work, I strengthen my English study and improve my English level by learning software. Now the project of Asia Aluminum continues. Up to now, I have found that I have adapted to this brand-new way of working, and I feel that I have the ability to continue this project until it is successfully completed.
In these three months, in addition to the xx project, I have also completed the following projects: gas engineering of staff canteen in xx building, air conditioning engineering of electronic air compressor room and refrigeration room, gas engineering of xx (completed), and preliminary design of new factory building of xx mold. Through the completion of the above work, I have a more comprehensive understanding of my work, and I also realize that as an engineer of xx, I should have a good learning attitude and method, a solid professional foundation and familiar design software operation ability, dare to put forward my own ideas and programs, and dare to innovate! Of course, good language skills are essential for communicating with leaders and colleagues and putting forward their own ideas.