What are the upfront costs of construction projects?
The preliminary work expenses of a construction project refer to the expenses incurred in the preliminary work such as project planning, feasibility study and preliminary design before the construction project starts. Before the project is established, the competent department of the project shall pay according to the annual investment plan and the capital construction expenditure budget, the approved preliminary work content and work progress; After the project is approved, the construction unit shall be responsible for the use and management, and pay the fees according to the terms stipulated in the survey and design contract. The payment requirements shall be strictly controlled within the issued investment plan and approved work contents, and it is strictly forbidden for the competent department of the project and the construction unit to intercept, misappropriate and transfer the preliminary work fees. I'm not from Liaoning, so I can't provide further information. If your project is government funds, you must be cautious.

If you want to know about the government fees in the early stage of construction projects, it is roughly as follows:

I. Direct payment for construction projects:

1, supporting fee; Construction bureau levy

2. Civil air defense fees; (If your project is designed with civil air defense works, it is not needed. ) This was collected by the Civil Defence Office.

3. Construction waste disposal fee; This is collected by the environmental health department.

4. Quality supervision fee; Collection by quality supervision station

5. Wall Material Fund; Planning bureau collects

6, bulk cement fund; Construction Bureau (with bulk cement office)

7. Fixed management fee; construction bureau

8. Construction of urban public facilities (sidewalks and street trees corresponding to construction land, etc. ); Construction bureau. If it is done according to the requirements of the construction bureau, it will not be accepted.

9. Application fee; Archives collection of construction bureau

Second, land acquisition, environmental protection, planning and design:

1, EIA fee (collected by the Environmental Protection Department, give you an EIA report)

2. Expert review fee for environmental report assessment: charged by the Environmental Protection Bureau.

3. Drawing approval fee; (accepted by the engineering consulting unit)

4. Various design fees; Don't talk about it

5. Urban land use tax, land occupation tax, deed tax, cultivated land transformation fee, land transfer fee, land acquisition fee, young crops fee, resettlement fee and relocation fee. (Collected by Land and Resources Bureau and Tax Bureau)

Three, water, electricity, gas, communications, transportation and other expenses (generally there are fees, directly included in the construction cost).

Generally speaking, government administrative service centers have a guidebook, which you can read clearly.